Delay Alert — DLY-2026-042
Mobile + Email notification • Purification skid foundation 9 days behind, trend slipping
CRITICAL
⚠
Purification Skid Foundation — 9 Days Behind
Trend: Slipping 📉 | Area: Upgrading / Purification
Alert Details
Alert ID: DLY-2026-042
Raised: 13 Nov 2026, 14:22 (Auto-detected from AeroBuild capture)
Baseline Date: 15 Jan 2027 (Foundation Complete)
Current Forecast: 24 Jan 2027
Variance: 9 calendar days (6 working days)
Trend: Worsening — was 5 days behind on 08 Nov
Confidence: 87% (based on 3 capture dates + site reports)
Impact on Critical Path: Direct — delays Purification Skid Delivery (20 Jan) → First Gas (15 Apr)
Root Cause Analysis
Primary: Excavation dewatering took 4 days longer than planned due to high water table
Secondary: Rebar cage fabrication delayed 3 days — vendor capacity constraint
Contributing: Two rain days (09-10 Nov) halted concrete pour
Evidence & Links
RK
Owner: Rajesh Kumar (Civil Lead)
[email protected] | +91-98765-43210
[email protected] | +91-98765-43210
VP
Escalation: Vijay Patel (Project Manager)
[email protected] | +91-98765-43211
[email protected] | +91-98765-43211
Mobile Notification Preview
07:15
📶 🔋 87%
🌿
Garuda Greens Platform
Critical Alert • 2 min ago
⚠ Purification Skid: 9 Days Behind
Trend slipping • Direct critical path impact
EMAIL PREVIEW
Subject: [CRITICAL] Delay Alert DLY-2026-042 — Purification Skid Foundation 9 Days Behind
To: [email protected], [email protected]
Body: Auto-detected via AeroBuild capture comparison (08 Nov vs 14 Nov). Foundation excavation dewatering +4 days, rebar fabrication +3 days, rain +2 days. Critical path impact: Purification skid delivery (20 Jan) at risk. View in Platform →
To: [email protected], [email protected]
Body: Auto-detected via AeroBuild capture comparison (08 Nov vs 14 Nov). Foundation excavation dewatering +4 days, rebar fabrication +3 days, rain +2 days. Critical path impact: Purification skid delivery (20 Jan) at risk. View in Platform →